Guangxi Jiakai chemical 6000 ton industrial coating project EIA secondary publicity

Guangxi Jiakai chemical 6000 ton industrial coating project EIA secondary publicity

March 30, 2011

[China coating information] i. overview of the construction project

the plastic in the mixer has completely become powdery materials

Guangxi Jiakai Chemical Technology Co., Ltd. plans to build a 6000 ton annual output industrial coating project in Liujiang County emerging industrial park, Liuzhou city. It is proposed to build a new paint production workshop and supporting auxiliary facilities, and build a domestic advanced paint production line. The production plan mainly includes car paint, truck paint, engineering machinery paint and heavy-duty anti-corrosion paint. The company covers an area of 73.699 Mu and the construction investment is 46.0372 million yuan

II. Discharge of major pollutants and environmental protection measures of the construction project

⑴ wastewater

the sewage produced in the production process of the project includes equipment cooling water and a small amount of staff domestic sewage. The equipment cooling water is recycled and not discharged, but only the evaporation loss is supplemented

⑵ exhaust gas

the atmospheric pollutants of the project are mainly organic gases volatilized by organic solvents. Due to the closed operation of the process operation process, the volatilization of organic solvents can be minimized through the synergy between the three

the construction unit plans to set up an air supply and exhaust system in the paint production workshop and warehouse, and an activated carbon adsorption device is added to the exhaust system to adsorb organic solvent gas with activated carbon. After treatment, the waste gas is discharged through a 15m high exhaust funnel. After the treatment of the organic waste gas of this project, the emission concentration of xylene and non methane total hydrocarbon meets the requirements of GB "standard for comprehensive emission of air pollutants but three stars have a special preference for plastics, which is also quite rare in the industry"

install a gas collecting hood above the feeding port of the equipment adding pigments. After feeding, close the feeding port immediately through the controllable switch, and start the gas collecting hood at the same time. Collect a small amount of waste gas containing dust and discharge it after treatment by the bag filter. The dust recovered from the bag can be reused as raw materials. The emission concentration of dust containing waste gas after collection and treatment by bag filter is generally lower than 10mg/m3, which meets the maximum allowable emission concentration of 120mg/m3 of particulate matter in GB integrated emission standard of air pollutants

⑶ solid wastes

waste solvents, waste filter cotton and other hazardous wastes are classified as HW12. They are temporarily stored in temporary collection containers for hazardous wastes in the plant, and Liuzhou Golden Sun industrial waste disposal Co., Ltd. and other qualified units are entrusted to treat the hazardous wastes without discharging them outward

⑷ noise

the production noise source of the proposed project is mainly the noise generated by air compressors, horizontal sand mills, high-speed dispersers, platform color mixing cylinders, air compressors, automatic solvent delivery lines, etc., with a noise value of 72 ~ 95 dB. The air compressor station building is set independently, and the working room and operation room are separated, and the wall adopts the Mullah wall. The air compressor adopts a low-noise screw air compressor, and a muffler is installed at the air outlet to reduce the noise. The equipment adopts independent foundation, vibration pads, wall sound absorption and insulation, and operators wear protective plugs, protective masks and other prevention measures. To ensure the accuracy of measurement data

III. analysis of environmental impact prediction results

by adsorbing organic solvent gas with activated carbon, the emission concentration of xylene and non methane total hydrocarbons meets the requirements of GB integrated emission standard of air pollutants. The dust containing waste gas is collected by the gas collecting hood and discharged after treatment by the bag filter. The dust emission concentration meets the requirements of the maximum allowable emission concentration of 120mg/m3 of particulate matter in GB integrated emission standard of air pollutants. It is predicted that the ambient air will not be affected by the air pollution of the project

the cooling water of the equipment is recycled without being discharged. The domestic sewage is treated in the septic tank and then discharged into the Liujiang River after reaching the standard in the sewage treatment station of Xinxing Industrial Park, which has little impact on the water quality and environment of Liujiang River

the project is produced in two shifts every day, and the daytime noise at the plant boundary meets the requirements of class 3 standard of GB emission standard of environmental noise at the boundary of industrial enterprises, which has little impact on the environment

IV. method and deadline for viewing the simplified report

ask for it at No. 1408, Dadong digital international commercial and residential building, Sanzhong Road, Liuzhou city from March 12 to March 25, 2011

v. feedback method of public opinions

the public can express their opinions and opinions on the project construction and environmental assessment work by sending e-mail, fax, letter or interview within 10 working days after this publicity

(1) Guangxi Jiakai Chemical Technology Co., Ltd.

Contact: Xia Bilai:

(2) Shenzhen Environmental Engineering Science and technology center

Contact: Wang Jie

(fax):

e-mail:lzxiaolading@

Shenzhen Environmental Engineering Science and technology center

March 12, 2011